$300 million: Value of the construction contract with Boreal Health Partnership
$350 million: Total capital cost of the construction project including costs incurred by the Government of the Northwest Territories. The $50 million in extra costs will pay for:
- clinical information system
- FF&E
- project management
- engineering
- financial advisors
- lawyers
- honoraria to the unsuccessful proponents
$751 million: Value of contract with Boreal Health Partnership (BHP). $70 million: Amount identified by BHP as available for local contractors to benefit from the project, both in construction phase and maintenance post-construction.
$1.1 billion: Cost of a traditional design and build for a new Stanton Territorial Hospital, including 30 years of operation and maintenance.
25 percent: Approximate savings to GNWT through P3 process over traditional design and build option, approximately $290 million.
2015: Construction will begin in Fall 2015.
2018: Construction is expected to be completed in late-2018.
2021: Expected year the new Stanton Territorial Hospital will be fully operational.
100: Number of beds in the new Stanton Territorial Hospital
280,000: Total size (square-foot) of new building, approximately double the size of the current facility.